A 38KV grid connection cable and associated infrastructure to connect the approved Johnstown North solar farm (consented under planning ref. 171497) to the existing Arklow 220kV Substation comprising the laying of a 3,190m Underground Cabling (UGC) and associated infrastructure, located at Dublin Road, Arklow, Co. Wicklow
- Applicant
- Not published
- Authority
- Wicklow County Council
- Decision due
- 20 Mar 2024
Timeline
Application received
14 Jul 2023
Council asked for further information
31 Aug 2023
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
22 Feb 2024
Decision due
20 Mar 2024
Decision: conditional
20 Mar 2024
Grant issued
23 Apr 2024
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
demolition of existing single storey shed and garage to rear, construction of new part single storey part storey and a half extension containing 2 dormer windows to rear, removal of existing septic tank and new replacement proprietary effluent treatment system and all associated site works
to amend the design of the approved development (Planning Reference: 17/1497) which comprises a Solar PV Energy Development. Proposed amendments include (1) change in location and size of substation, (2) two additional temporary construction compounds will be located at the site entrances, (3) the number of modules will decrease, (4) the number of pile driven poles will decrease, (5) the size and number of transformer stations will increase, (6) the total fencing area will increase (7) the total amount of fencing posts will increase, (8) up to 21 CCTV cameras will be installed (9) access tracks will be optimised and increased in width and length, and (10) increase in operational lifetime from 25 years to 35years
construction of a bungalow with garage and car port, new entrance and access driveway, new treatment system and percolation area to current EPA standards and all ancillary site works
demolition of existing storage shed, a new shed to serve as house ancillary storage and hobby shed to store vintage cars and associated site development works
demolition of existing storage shed, a new storage shed and associated site development works
demolition of existing storage shed, a new storage shed and associated site development works