BALLYKILLEEN TOWNLAND, CO. OFFALY, (WITHIN THE PREVIOUSLY CONSENTED CLONCREEN WIND FARM - ABP REF PL19.PA0047)
Proposed development
A MODULAR BATTERY ENERGY STORAGE SYSTEM (BESS) FACILITY WITHIN THE FOOTPRINT OF A PREVIOUSLY CONSENTED CONSTRUCTION COMPOUND (ABP REF. PL19.PA0047). PLANNING PERMISSION IS SOUGHT FOR A PERIOD OF 10 YEARS. THE FACILITY WILL CONSIST OF UP TO 28 NO. BATTERY STORAGE MODULES (UP TO 13M IN LENGTH, 3M IN WIDTH AND 3M IN HEIGHT) AND ANCILLARY EQUIPMENT INCLUDING UP TO: 28 NO. STEP-UP TRANSFORMERS, 28 NO. AIR-HANDLING UNITS AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS AND SERVICES, INCLUDING LIGHTNING PROTECTION MONOPOLES; COLUMN LIGHTING AND CCTV CAMERAS; INTERNAL ACCESS ROADS JOINING THE BESS FACILITY WITH THE CONSENTED CLONCREEN WIND FARM ROAD NETWORK; SECURITY FENCING; SITE DRAINAGE AMENDMENTS; AND UNDERGROUND ELECTRICAL CABLE, AS REQUIRED TO FACILITATE THE DEVELOPMENT AND WILL INVOLVE THE CONTINUED USE OF THE CONSENTED CONSTRUCTION COMPOUND. THE BESS FACILITY WILL BE LOCATED ENTIRELY WITHIN THE BOUNDARY OF THE CONSENTED CLONCREEN WIND FARM AND WILL USE EXISTING ACCESS ARRANGEMENTS WITHIN THE WIND FARM. THE APPLICATION IS ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS)
- Applicant
- Not published
- Authority
- Offaly County Council
- Decision due
- 2 Aug 2021
Timeline
Application received
9 Feb 2021
Council asked for further information
1 Apr 2021
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
8 Jun 2021
Decision due
2 Aug 2021
Decision: conditional
30 Jul 2021
Grant issued
6 Sept 2021
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
(RED III) a period of 10 years for a grid connection for the previously approved, but not yet constructed, solar energy development (Planning ref: 21/598). This will consist of installation of medium voltage (MV) electrical cabling between the solar arrays and the existing Philipstown 110kV substation, including a 8m section of cable within the R401 and a 56m section of overhead line and associated pole sets to facilitate crossing of the Figile River. A Natura Impact Statement (NIS) has been submitted as part of the application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413)
New site entrance arrangements, replacing the previously consented access points 3 and 4 approved under Planning Reference 21/598, together with associated internal access tracks, drainage systems and all related works
Permission for development at this site within the townlands of Ballykilleen, Ballinowlart North and Kilcumber, Co. Offaly. The development will consist of: 1. A grid connection for the previously approved, but not yet constructed, solar energy development (Planning ref: 21/598). This will consist of medium voltage (MV) electrical cabling between the solar arrays and the existing Philipstown 110kV substation, including a 8m section of cable within the R401 and a 56m section of overhead line and associated pole sets to facilitate crossing of the Figile River. 2. Amendments to the previously approved, but not yet constructed, solar energy development (Planning ref: 21/598) comprising revised site entrance arrangements in place of permitted access points 3 and 4 including associated internal access tracks, drainage and development boundary amendments.
DEVELOPMENT AT EDENDERRY POWER PLANT. EDENDERRY POWER LIMITED CURRENTLY HAS PLANNING PERMISSION TO OPERATE EDENDERRY POWER PLANT AS A PEAT AND BIOMASS CO-FIRED POWER PLANT UNDER GRANT OF PLANNING PERMISSION (OFFALY COUNTY COUNCIL REGISTER REFERENCE - PL2/15/129, AN BORD PLEANÁLA REGISTER REFERENCE - PL 19.245295). THE PROPOSED DEVELOPMENT WILL CONSIST OF THE CONTINUED OPERATION OF EDENDERRY POWER PLANT FROM THE BEGINNING OF 2024 TO THE END OF 2030 EXCLUSIVELY USING SUSTAINABLE BIOMASS FUEL. THE APPLICANT PROPOSES TO INCREASE THE VOLUME OF BIOMASS CONSUMED AT THE FACILITY FROM A CURRENT MAXIMUM OF 300,000 TO 530,000 TONNES PER ANNUM. IT IS PROPOSED TO UTILISE THE EXISTING PERMITTED ELECTRICITY GENERATION STATION AND INFRASTRUCTURE, INCLUDING FUEL HANDLING SYSTEMS, UTILITIES, PROCESSING SYSTEMS AND ANCILLARY STRUCTURES AS PART OF THE PROPOSED DEVELOPMENT. THERE WILL BE NO CHANGE TO EXISTING INFRASTRUCTURE PRESENT ON-SITE. SITE ACCESS AND EGRESS WILL USE THE EXISTING PERMITTED SITE ENTRANCES TO THE R401 PUBLIC ROAD. THERE WILL BE NO CHANGE TO THE PERMITTED BOUNDARY OF THE FACILITY. EDENDERRY POWER PLANT IS LICENCED BY THE ENVIRONMENTAL PROTECTION AGENCY UNDER AN INDUSTRIAL EMISSIONS (IE) LICENCE [REF. P0482-04]. ACTIVITIES AT THE FACILITY AND ASSOCIATED ENVIRONMENTAL ASPECTS AND EMISSIONS WILL CONTINUE TO BE REGULATED AND CONTROLLED BY THE EPA. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR). THE PLANNING APPLICATION IS ALSO ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS)
THE CONTINUED USE OF A CONSENTED CONSTRUCTION COMPOUND (PL19.PA0047) AS A MODULAR BATTERY ENERGY STORAGE SYSTEM (BESS) FACILITY. PLANNING PERMISSION IS SOUGHT FOR A PERIOD OF 10 YEARS. THE FACILITY WILL CONSIST OF: UP TO 28 NO. BATTERY STORAGE MODULES (UP TO 13M IN LENGTH, 3M IN WIDTH AND 3M IN HEIGHT) AND ANCILLARY EQUIPMENT INCLUDING UP TO: 28 NO. STEP-UP TRANSFORMERS, 28 NO. AIR HANDLING UNITS AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS AND SERVICES, INCLUDING LIGHTNING PROTECTION MONOPOLES; COLUMN LIGHTING AND CCTV CAMERAS; INTERNAL ACCESS ROADS JOINING THE BESS FACILITY WITH THE CONSENTED CLONCREEN WIND FARM ROAD NETWORK; SECURITY FENCING; SITE DRAINAGE AMENDMENTS; AND UNDERGROUND ELECTRICAL CABLE, AS REQUIRED TO FACILITATE THE DEVELOPMENT. THE BESS FACILITY WILL BE LOCATED ENTIRELY WITHIN THE BOUNDARY OF THE CONSENTED CLONCREEN WIND FARM AND WILL USE EXISTING ACCESS ARRANGEMENTS WITHIN THE WIND FARM. THIS APPLICATION IS ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS).
ALTERATIONS TO THE EXISTING 110KV CUSHALING SUBSTATION AND INCLUDES THE INSTALLATION OF 110KV AIS SWITCHGEAR WITH ASSOCIATED FOUNDATIONS, STEELWORK, SUPPORTS AND CONNECTORS AND ASSOCIATED WORKS