Dundrumman, Scotstown, Co. Monaghan
Proposed development
Permission to erecting a 850kW Wind Turbine, located at the North area of our existing plant; the Wind Turbine will be installed with a hub height of 65 meters and a blade radius of 26 meters, with underground ducting connecting to the existing ESB substation and all associated site works. A Natura Impact Assessment (NIS) will be submitted to the Planning Authority in connection with the application described above, Significant Further Information received relates to submitted, Assessment of landscape & Visual Impact, Proposed Wind Turbine Development Photomontage report, Shadow Flicker Report, Noise Assessment, Veon Ecology Letter, 4 letters of consent from neighbour dwellings, revised site layout plan, revised site location map, revised record map
- Applicant
- Not published
- Authority
- Monaghan County Council
- Decision due
- 24 Aug 2025
Timeline
Application received
4 Sept 2024
Council asked for further information
29 Oct 2024
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
28 Jul 2025
Decision due
24 Aug 2025
Decision: refused
22 Aug 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
permission to erect a 850 kW wind turbine located in the northern area of our existing plant, with a hub height of 65 metres and a blade radius of 26 metres, together with underground ducting connecting to the existing ESB substation and all associated site works. A Natura Impact Assessment (NIS) will be submitted to the Planning Authority in connection with the application described above. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413). Significant further information received relates to submitted revised CEMP, Ornithology report, Revised Natura Impact report, Water framework compliance assessment and Updated planning report.
erecting a 850kW Wind Turbine, located at the North area of our existing plant; the Wind Turbine will be installed with a hub height of 65 meters and a blade radius of 26 meters, with underground ducting connecting to the existing ESB substation and all associated site works
Permission to erect a two storey dwelling house, insert a filter unit and percolation area and exit on to public road by way of existing laneway.
permission to construct a new bungalow style dwelling house & detached domestic garage, install new mechanical effluent treatment system, raised / mound soil percolation area, construct new domestic entrance together with all ancillary site works
permission for retention of a development consisting of 1) elevational changes, 2) internal alterations to accommodate 1st floor accommodation 3) agricultural outbuilding to keep horses (exempt development) 4) all associated works
permission to demolish existing derelict two storey dwellinghouse and ancillary outbuildings and construct a new replacement two storey dwellinghouse and detached domestic garage, install new mechanical effluent treatment system, new mounded percolation area, develop existing domestic entrance together with all ancillary site works