Bonestown, Dunshaughlin, Co Meath
Proposed development
Two buildings for the manufacture of building materials arranged on two self-contained sites together with an access road, landscaping, boundary treatments, car parking, bicycle parking, bin storage, signage, ESB substation and all associated site development works including drainage pipework and connections, utility services and public lighting, The total site area is 4.88ha. Building 1 will be used for the manufacture of insulated formwork for the construction industry and will have a gross floor area of approx. 2794sqm. This includes ground floor production area and storage areas together with an office/showroom/training space arranged over two floors. The site for Building 1 will include for a hardstand external storage area, a circulation roadway, car parking, bicycle parking, bin storage, landscaping, boundary fencing and gates, signage and all associated site development works. Building 2 will be used for the manufacture of precast concrete products for the construction industry and will have a gross floor area of approx. 5386sqm (inclusive of office space over two floors). The site for Building 2 will include for hardstand external storage area, a circulation roadway, car parking, bicycle parking, bin storage, landscaping, boundary fencing and gates, signage and all associated site development works
- Applicant
- Not published
- Authority
- Meath County Council
- Decision due
- 15 Feb 2022
Timeline
Application received
13 Dec 2021
Decision due
15 Feb 2022
Decision: refused
14 Feb 2022
Appeal decided: withdrawn (ABP-312992-22)
Not available
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
the development consists of the following: Planning for: 1) provision of additional car parking spaces (2) increase of child capacity from 65 to 77 children, Retention of: 3) amendments and alterations to elevations and floor plans from that previously granted under ref 01905 (4) Retention of single storey lean roof over play area to the rear and side (5) all facility and ancillary site works
the development consists of the following: Retention of: 1) amendments and alterations to elevations and floor plans from that previously granted under ref 01905 (2) Retention of single storey lean roof over play area to the rear (3) provision of additional car parking spaces (4) increase of child capacity from 65 to 77 children (5) all facility and ancillary site works
EXTENSION OF DURATION OF PLANNING PERMISSION 2560158 - Strategic Housing Development (Subsequently amended under MCC Reg. Ref. 25/60158) for the development of 190 no. units, creche, public open spaces and associated works. Please refer to the Planning Letter for full development description
the development consists of the construction of a single-storey shed and pergola to the side of the house
the development will consist of: A) a single story 77 sqm granny flat extension to the West and South elevations of existing house comprising of 2 bedroom, 1 Bathroom, Utility and Kitchen/sitting room area. B) some window configurations to the existing house main kitchen window to a sliding door. Septic tank and percolation area, landscaping and all associated works.
The proposed Large Scale Residential Development (LRD) will consist of amendments to the Strategic Housing Development (SHD) permitted on site under Ref. ABP-307244-20 for 211 no. residential units (112 no. two storey houses and 99 no. apartments in 6 no. blocks), creche and associated works. This amendment application seeks to omit permitted apartment Blocks D and E (comprising 36 no. units) and replace with 15 no. 3 bed houses, resulting in a revised residential development of 190 units in total. Omission of permitted access road from the permitted Distributor Road to the east and associated amendments to residential car parking and provision of additional open spaces. All other site works including boundary treatments, landscaping and site services to facilitate development. The remainder of the development to be carried out in accordance with the parent permission Ref. ABP-307244-20