Coolaboy, Dromcollogher, Co. Limerick.
Proposed development
Existing foundations. Permission is sought for revised foundations, the construction of a new dwelling house, detached domestic garage, vehicular entrance, septic tank, percolation area and all associated site works
- Applicant
- Not published
- Authority
- Limerick City and County Council
- Decision due
- 27 Oct 2024
- Residential units
- 1
- Floor area
- 190.4 m²
Timeline
Application received
11 Jun 2024
Council asked for further information
1 Aug 2024
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
30 Sept 2024
Decision due
27 Oct 2024
Decision: conditional
25 Oct 2024
Grant issued
29 Nov 2024
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
construction of two detached, two-storey, two-bed dwellings with two off-road parking spaces, gardens, enclosures and all ancillary siteworks and services
detached garage and storage shed as constructed
a new footbridge over river with edge protection & connecting paved link between the church grounds & the town park lands & all associated site works (The proposed works are in the Curtilage of a protected structure)
Uisce Éireann intends to apply for a 10-year planning permission to construct a new wastewater treatment plant (WwTP) at Coolaboy, Dromcollogher, Co. Limerick. The Proposed Development will comprise the construction of a new WwTP to provide treatment capacity for a population equivalent (PE) of 1,350 (10 years) and 1,550 (30 years). The wastewater will be treated and discharged via an outfall pipe into the River Deel at a location approximately 6.5 kilometres to the northwest of the WwTP. The outfall pipe will be located primarily in public roads in the townlands of Coolaboy, Mundellihy, Ballinlongig, Cloonmore and Tulligmacthomas. The existing WwTP will be decommissioned and demolished upon completion of the Proposed Development. The Proposed Development will comprise: i) Development of a new preliminary wastewater treatment plant including infrastructure such as bypass channels and screens; grit and fats, oils, greases (FOG) removal plant; storm water overflow tank; sludge drying reed beds; flash mixer chamber; return liquor pumping station facilities; caustic and ferric dosing storge tanks; flow to full treatment (FFT) pumping station; final settlement tank flow split chamber; 2 no. final clarifiers; sludge draw off chamber (return-activated sludge and waste-activated sludge pumping station); static mixer; wash water pumping station; tertiary disk filter; and final effluent pumping station. ii) Development of an ESB sub-station, control building, and fuel tank. iii) Provision of approx. 54m of new gravity sewer to direct flows to the new WwTP. This will replace an existing combined sewer overflow which will be decommissioned after the process switchover. iv) Provision of adequate site lighting, access gates, access stairs, walkways, car parking and electric charging facilities, and site boundary hedging and fencing. v) Provision of photovoltaic (PV) panels on the site of the existing WwTP following its decommissioning. vi) Provision of site drainage infrastructure including a hydrocarbon interceptor, construction of outfall pipe along public roads, and headwall in Tulligmacthomas. vii) Realignment and widening of existing site entrance, including provision of a new access road into the site and a bridge within the site. viii) All hard and soft landscaping throughout the site, and all associated and ancillary site works. The Proposed Development will be accompanied by a Natura Impact Statement (NIS)
a new public walkway link between the church carpark & town park lands & associated site works
planning reference number 22/1153; the construction of a dwelling house, detached domestic garage, connection to public foul sewer, new vehicular entrance and carry out all associated ancillary site works