Luddenmore, Grange, Kilmallock Co. Limerick.
Proposed development
The construction of a dwelling house, septic tank and percolation area, entrance walls, garage and all ancillary site works
- Applicant
- Not published
- Authority
- Limerick City and County Council
- Decision due
- 21 Aug 2019
- Residential units
- 1
- Floor area
- 118.28 m²
Timeline
Application received
25 Apr 2019
Council asked for further information
18 Jun 2019
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
25 Jul 2019
Decision due
21 Aug 2019
Decision: conditional
15 Aug 2019
Grant issued
18 Sept 2019
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
the development that will consist of the following works: (a) Demolition and removal of existing build on-site. (b) The construction of a new open cycle Turbine Power Generation Station with an output of up to 299 Megawatts. The proposed station will consist of 1 no. Gas Turbine and 1 no. 44 m high Exhaust Stack, 1no. AIS Substation and associated lighting column, 1 no. single storey Packaged Electronic/Electrical Control Compartment, 1 no. single storey Continuous Emission Monitoring System Shelter, Associated Fin Fan Coolers, 1no. Storage and Warehouse building, 1no. HVO fuel storage tank, 1no. dimineralised water storage tank, 1no raw/fire water storage tank, 1no. fire pump house, 2no. demineralised water treatment trailers. (c) The construction of an internal road network providing for access to serve the development. (d) Provision of hard and soft landscaping works, tree planting and boundary treatments including parking, perimeter fencing
the construction of a new dwelling, garage, wastewater treatment system & polishing filter, entrance and all associated site works
the demolition and removal of existing build on-site. The construction of a new Gas Fired open cycle Turbine Power Generation Station with an output of up to 293 Megawatts. The proposed station will consist of 1 no. Gas Turbine and 1 no. 44 m high Exhaust Stack, 1 no. AIS Substation and associated lighting column, 1 no. single storey Packaged Electronic/Electrical Control Compartment, 1 no. single storey Continuous Emission Monitoring System Shelter, Associated Fin Fan Coolers, 1no. Storage and Warehouse building, 1no. fuel oil storage tank, 1 no. dimineralised water storage tank, 1 no raw/fire water storage tank, 1 no. fire pump house, 2no. demineralised water treatment trailers. The construction of a internal road network providing for access to serve the development. Provision of hard and soft landscaping works, tree planting and boundary treatments including parking, perimeter fencing
the development that will consist of the following works: (a) demolition and removal of existing build on-site, (b) the construction of a new Gas Fired open cycle Turbine Power Generation Station with an output of up to 293 Megawatts. The proposed station will consist of 1 no. Gas Turbine and 1 no. 44 m high Exhaust Stack, 1 no. AlS Substation and associated lighting column, 1 no. single storey Packaged Electronic/Electrical Control Compartment, 1 no. single storey Continuous Emission Monitoring System Shelter, Associated Fin Fan Coolers, 1no. Storage and Warehouse building, 1no. fuel oil storage tank, 1no. dimineralised water storage tank, 1no raw/fire water storage tank, 1no. fire pump house, 2no. demineralised water treatment trailers, (c) the construction of a internal road network providing for access to serve the development, (d) provision of hard and soft landscaping works, tree planting and boundary treatments including parking, perimeter fencing
a single storey rear extension to an existing two storey dwelling house, modifications to the existing external elevations including alterations to windows, external façade, and all ancillary site works. Retention permission is also being sought for an existing front porch and all ancillary site works