ObjectRight
Back to search
191250Grantedpermission

Milltown & Coolyhenan, Co. Limerick.

Not open for objections: The council has already decided this application.

Proposed development

Minor modifications to a previously permitted development (Ref. 12/1002). The proposed development comprises the extension of the existing Killonan 220/110 kV Electrical Substation compound by approx. 0.5ha along and adjacent to its existing western boundary. This will facilitate the proposed siting of a previously permitted Line Cable Interface Mast (LCIM) development includes the associated erection of 2.6m high palisade fencing along the extended western boundary of the substation compound and all associated and ancillary development at the existing Killonan 220/110 kV Electrical Substation

Applicant
Not published
Authority
Limerick City and County Council
Decision due
19 Feb 2020
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    17 Dec 2019

  2. Decision due

    19 Feb 2020

  3. Decision: conditional

    18 Feb 2020

  4. Grant issued

    24 Mar 2020

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2660923Refused

- the construction and operation of a wellness facility incorporating 2no. sauna cabins, 4 no. cold plunge tubs, 2no. changing area, 1no. WC, reception area, maintenance yard and associated ancillary structures - Installation of wastewater treatment facilities and all associated site works - Provision of 14no. car parking, 8no. bicycle parking, signage, landscaping, boundary treatments and connection to existing services - And all ancillary and associated development works above and below ground

Ballysimon Commons, Co. Limerick Limerick City and County Council Received 12 Aug 2026
2660401Granted

extensions previously constructed to the rear of existing dwelling and all associated site works

Oak Cottage, Coolyhenan, Ballysimon Limerick Limerick City and County Council Received 9 Apr 2026
24344Granted

the development that will consist of: The installation of solar panels on 2 no. steel frames over each roof of 2 no. existing telecommunication cabins (covering an area of approx. 46 sq.m. and approx. 32 sq.m. respectively, each to a maximum height of 4.5 metres above ground level). Works to consist of all ancillary development works including steel uprights

ESB's Killonan 220kV Substation, Milltown, Killonan Limerick City and County Council Received 6 Sept 2024
237011Granted

extension of permission for planning ref 12/1002: an electrical transmission substation and associated infrastructure and works, within and adjacent to the site of the existing 220/110kV Killonan substation. The development consists of (1) construction of a 220kV Gas Insulated Switchgear (GIS) substation building, of 1,856m2 gross floor area, with a maximum height of approximately 14 metres above ground level, (2) construction of a 110kV GIS substation building of 1,642m2 gross floor area, with a maximum height of approximately 12.5 metres above ground level, (3) construction of associated and ancillary outdoor electrical equipment and other apparatus; construction of three lightning masts of approximately 18.4 metres in height; internal access road, car parking areas, boundary treatment, associated drainage and site development works, (4) associated transfer of circuits from the existing 220/110kV Air Insulated Switchgear (AIS) substation to the proposed GIS substation, (5) construction of six 110kV end masts to facilitate connection of the existing overhead line transmission circuits to the proposed substation equipment by way of underground cable connections. These end masts will replace six existing end masts which are located within the existing ESB Killonan site. Two of the six end masts will be located adjacent to, but outside the western and southern boundaries of the existing substation complex. One of these two end masts will be located in the townland of Coolyhenan, the other will be in the townland of Milltown. The remaining 4 end masts and all other proposed works are located within the existing ESB Killonan substation in the townland of Milltown. The proposed end masts will measure up to a maximum of 21.5metres in height and will be of a similar form, scale and character to those existing and (6) all associated site development works (this application is for a 10 year permission)

Tds. of Milltown & Coolyhenan, Limerick City and County Council Received 11 May 2023
2360124Granted

the construction of a single story extension ( 13 sqm) to the side of existing Licensed premises, for the sale of take-away hot food & beverages accessed from existing car park, installation of a replacement waste water treatment system with polishing filter together with all associated site works

Morrisons bar & Grill, Milltown & Ballysimon Commons, Ballysimon Co. Limerick Limerick City and County Council Received 6 Mar 2023
22147Granted

amendments to planning permission 20/983. The development will comprise carrying out part demolition of, and revised alterations and extension to existing dwelling including all associated site development works

Oak Cottage, Coolyhenan, Ballysimon Limerick Limerick City and County Council Received 11 Feb 2022