Sherlockstown, Sallins, Co. Kildare
Proposed development
Retaining and completing alterations to a previously approved property to include a revised roof design, a single story extension of living space to the rear, and attic storage to garage, as currently under construction to property granted under planning file 16/1059 and extended by planning file 21/1386 ( currently under construction), and all associated auxiliary site works
- Applicant
- Not published
- Authority
- Kildare County Council
- Decision due
- 18 Apr 2023
Timeline
Application received
22 Feb 2023
Decision due
18 Apr 2023
Decision: conditional
6 Apr 2023
Grant issued
19 Jun 2023
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
retention of two dormer windows on rear slope and conversion of second floor to accessible storage space of existing dwelling. Retention of altered fenestration, extended living room into previous garage area, altered location and orientation of dwelling and altered sunroom external walls & roof from that granted under planning reference 99/726. Retention of rear porch area. Retention of structure and change of use of detached ancillary unit housing gym, study and games room with associated pumped discharge septic tank. Retention of brick and railing front boundary wall. All ancillary works
for the construction of a split level bungalow, secondary effluent treatment system, recessed entrance and all associated site works
for (A) change of use of existing dilapidated house to out-buildings for agricultural use, (B) construction of a replacement single storey type house. (C) The decommissioning of the existing septic tank and the installation of an Oakstown BAF wastewater treatment plant with polishing filter percolation area. (D) Garage / store for domestic use, (E) construction of new vehicular recessed entrance and access driveway to serve the dwelling and all associated site works. Revised by Significant Further Information which consists of: There is now a demolition component that was not previously advertised
for a proposed single-storey extension to the side of the house and all ancillary site works
for the construction of a split-level bungalow, secondary effluent treatment system, recessed entrance and all associated site works
for the construction of a split level bungalow, secondary effluent treatment system, recessed entrance and all associated site works