Timeline
Application received
12 Jun 2019
Council asked for further information
1 Aug 2019
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
24 Sept 2019
Decision due
21 Oct 2019
Decision: conditional
18 Oct 2019
Grant issued
26 Nov 2019
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
for the construction of a new single storey dwelling, including a new site entrance onto an existing shared private laneway that links to the R148, together with a new Waste water treatment system and percolation area, and all associated site works.
for the construction of a new single storey dwelling, including a new site entrance onto an existing shared private laneway that links to the R148, together with a new Waste water treatment system and percolation area, and all associated site works
the construction of a new single storey dwelling, including a new site entrance onto an existing shared private laneway that links to the R148, together with a new Waste water treatment system and percolation area, and all associated site works
for the construction of a new single storey dwelling, including a new site entrance onto an existing shared private laneway that links to the R148, together with a new Waste water treatment system and percolation area, and all associated site works
For 1) Retain the following: a) the partially constructed 2-story 15 bed staff accommodation; b) the demolition of outbuildings; c) wastewater treatment system; d) temporary portacabin office unit (for period of 5 yrs); e) construction delivery overflow area; f) perimeter site security fencing. 2) Permission is being sought to a) complete a partially constructed 15 bed staff accommodation; b) reconfigure the site entrance; c) add additional fencing; d)provide onsite parking; e) carry out all ancillary site works
1. Retain the following; a) The partially constructed 2 storey 15 bed staff accommodation; b) the demolition of outbuildings; c) wastewater treatment system; d) temporary portacabin office unit (for a period of 5 years); e) construction delivery overflow area; f) perimeter site security fencing; 2. Permission is being sought to; a) complete the partially constructed 15 bed staff accommodation b) reconfigure the site entrance; c) add additional fencing; d) provide onsite parking; e) carry out all ancillary site works