DERRA EAST, LISTOWEL, CO KERRY
Proposed development
RETAIN AND COMPLETE AGRICULTURAL SHED ON HIS LAND HOLDING
- Applicant
- Not published
- Authority
- Kerry County Council
- Decision due
- 8 May 2022
Timeline
Application received
9 Jul 2021
Council asked for further information
31 Aug 2021
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
25 Nov 2021
Decision due
8 May 2022
Decision: conditional
6 May 2022
Grant issued
10 Jun 2022
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
REDS III: The development will consist of a 10-year permission for a solar photovoltaic (PV) energy development on a site spanning approximately 138.9 hectares. It will consist of the construction of PV panels mounted on metal frames, 38 inverters, new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, 4 temporary construction compounds, drainage infrastructure, landscaping and all ancillary electrical infrastructure and associated works. A separate application for the associated grid route and future 110kV substation will be submitted to An Coimisiún Pleanála (ACP) as these proposed elements fall within the Strategic Infrastructure Development consent process under Section 182A of the Planning and Development Act 2000 (as amended).The Application Site will be accessed from four new access points off the R553, L6029 and L6028 and one existing access point off the L6037. The development is designed to operate for 40 years from the date of commissioning. A Natura Impact Statement (NIS) will accompany the planning application.
(a) Retain a stone area on his land holding (b) retain entrance and Planning Permission to erect an agricultural storage shed for storing fodder
RETAIN DOMESTIC GARAGE/UTILITY STORE WITH A LOFT AT FIRST FLOOR LEVEL ALSO TO RETAIN TURF SHED
RETAIN THEIR DOMESTIC GARAGE/UTILITY STORE AS CONSTRUCTED TO THE REAR OF THEIR SITE
CONSTRUCT A WASTE RECOVERY FACILITY FOR THE IMPORTATION OF WASTE MATERIAL COMPRISING OF SOIL AND STONE (17 05 04) TO RAISE AN AGRICULTURAL FIELD IN ORDER TO IMPROVE THE AGRICULTURAL OUTPUT OF THE FIELD. A NATURA IMPACT STATEMENT (NIS) HAS BE PREPARED AND WILL BE SUBMITTED WITH THIS APPLICATION
RETAIN AN EXISTING ACCESS AND PLANNING PERMISSION TO UPGRADE THIS ACCESS