REACASHLAGH, BLACKWATER, KILLARNEY
Proposed development
(A) DEMOLISH PART OF EXISTING COMMUNITY CENTRE, (B) PERMISSION TO RENOVATE AND CONSTRUCT AN EXTENSION ONTO THE EXISTING COMMUNITY CENTRE, CONSISTING OF A NEW ENTRANCE AREA, NEW GREEN ROOM, KITCHENETTE, MALE AND FEMALE TOILET FACILITIES, MALE AND FEMALE CHANGING FACILITIES, NEW STORAGE AREA AND NEW STAGE, (C) PERMISSION TO INSTALL A NEW MECHANICAL TREATMENT UNIT AND SOIL POLISHING FILTER UNIT AND (D) PERMISSION TO CONSTRUCT A NEW CAR PARK AND ALL SITE DEVELOPMENT WORKS
- Applicant
- Not published
- Authority
- Kerry County Council
- Decision due
- 17 Feb 2019
Timeline
Application received
10 May 2018
Council asked for further information
29 Jun 2018
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
20 Dec 2018
Decision due
17 Feb 2019
Decision: conditional
13 Feb 2019
Grant issued
20 Mar 2019
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
The development consists of (a) retention planning permission to retain the conversion of the attic space to habitable accommodation, (b) retention planning permission to retain elevational changes made to the design of the house, (c) retention planning permission to retain the domestic shed as constructed, (d) retention planning permission to retain the roadside and entrance fencing as constructed, and (e) retention planning permission to retain the house, shed, wastewater treatment system, bored well, site entrance, driveway and parking area within revised site boundaries and Full Planning Permission to decommission the existing septic tank and to replace it with a new wastewater treatment system
CONSTRUCT A TWO STOREY DWELLING HOUSE, INSTALL A 'TRICEL NOVO' WASTEWATER TREATMENT UNIT FOLLOWED BY 2 NO. PURAFLO PEAT FILTERS TO SERVE THE DWELLING, UPGRADE EXISTING SITE ENTRANCE TO FACILITATE THE DEVELOPMENT AND ALL OTHER ASSOCIATED SITE WORKS