Main Street Ballineen, Enniskeane Co. Cork
Proposed development
Permission for retention of existing dwelling and associated site works to the east of The Olympic Tavern public house
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 21 Jan 2022
Timeline
Application received
18 Nov 2021
Decision due
21 Jan 2022
Decision: conditional
20 Jan 2022
Grant issued
23 Feb 2022
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
10 year permission for (1) new enclosed warm-up area to replace existing grass pitch (2) Removal of existing concrete crank post and wire fence and erection of new 1.20m high parameter fencing, (3) erection of 2nd-Ball-Stops to replace existing, (4) Provision of 1.80m wide footpath around pitch, (5) Erection of 21.0m high floodlighting masts to serve all weather/astro turf pitch (change of plan from that permitted under Planning Ref. 25/00015, (6) Provision of dugouts and scoreboard and all associated site works
Permission for the change of use of an existing community hall to a pre-school, including the construction of a new prefabricated single storey building (to accommodate toilets) to the rear of the existing building and all associated siteworks
Permission for development which consist of 2 no. sites (Site A) the existing wastewater treatment plant (WwTP) and (Site B) at the proposed wastewater treatment facilities on a new site
Uisce Eireann intends to apply to Cork County Council for permission for development which consist of 2 No sites (Site A) the existing wastewater treatment plant (WwTP) and (Site B) at the proposed wastewater treatment facilities on a new site both located in Derrigra, Ballineen, Co Cork.
Construction of 6 no. 4 metre high column lights to illuminate a walkway, and the upgrade of an existing 1.8 metre wide walkway with a tar finish and the installation of 6 no. 18 metre high floodlights and all associated site works
Construction of a new 1.8 metre wide footpath, and the installation of 13 no. 18 metre high floodlights, and all associated site works