Grangeford Old, and Friarstown, Co. Carlow
Proposed development
10 Year permission for development consisting of the construction of a Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area will be ca. 65.6 ha, the construction of a 38kV substation (ca 114.4m2 x 4.75 tall) a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2), along with ancillary development including; 24 no. Power Hubs (ca. 15.25m2 x 2.4m) which incorporate an inverter and a transformer, 1 no. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9m), 1 no. single storey equipment storage building (7.5m2 x 2.7m), 10 no. CCTV cameras mounted on 4m high poles, perimeter security fencing, site access, site egress and all ancillary works. Permission currently exists for a PV development on part of the site (Planning Permission Ref No. 16325). An Natura Impact Statement will accompany the planning application.
- Applicant
- Not published
- Authority
- Carlow County Council
- Decision due
- 25 Mar 2021
- Residential units
- 1
- Floor area
- 1 m²
Timeline
Application received
29 Jan 2021
Decision due
25 Mar 2021
Decision: refused
25 Mar 2021
Grant issued
26 Oct 2021
Appeal decided: conditional (309987-21)
26 Oct 2021
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
10-year permission. The development will consist of the construction of (i) a Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 91.2ha, (ii) the construction of a 38kV substation building ((6.1m (h) x 20.9 (l) and 7.3 (w)) and associated compound area, a transformer unit (ca. 6m x ca. 3.6m) and associated bund, (iii) 352 number Battery Energy Storage System units comprising 22 modules (ca. 21.9m x ca.5.2m) each with 16 number cabinet units within each module and (iv) all ancillary development including 15 number transformer integrated units (ca. 10.5m x ca.2.7m), 12 number inverter units (ca. 6.0m x ca.2.4m), 7 number CCTV cameras mounted on 4m high poles, a 3m high acoustic barrier, with berm and fencing, perimeter security fencing, site access, site egress and all ancillary works and services. The development will have a 40-year operational lifetime. Permission currently exists for a PV development on ca/65.6ha of the site (Planning Permission Ref No. 21/23) that will be superseded by this application if approved
10-year permission. The development will consist of the construction of (i) a Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 91.2ha, (ii) the construction of a 38kV substation building ((6.1m (h) x 20.9 (l) and 7.3 (w)) and associated compound area, a transformer unit (ca. 6m x ca. 3.6m) and associated bund, (iii) 352 number Battery Energy Storage System units comprising 22 modules (ca. 21.9m x ca.5.2m) each with 16 number cabinet units within each module and (iv) all ancillary development including 15 number transformer integrated units (ca. 10.5m x ca.2.7m), 12 number inverter units (ca. 6.0m x ca.2.4m), 7 number CCTV cameras mounted on 4m high poles, a 3m high acoustic barrier, with berm and fencing, perimeter security fencing, site access, site egress and all ancillary works and services. The development will have a 40-year operational lifetime. Permission currently exists for a PV development on ca/65.6ha of the site (Planning Permission Ref No. 21/23) that will be superseded by this application if approved
change of use of an existing shed from an agricultural store, to include the storage of treated biosolids for its future use as fertilizer/soil conditioner as part of existing agricultural operations
1. retention permission for a domestic shed as constructed, 2. permission for completion of same and all associated site works
for 1. retention permission for a domestic shed as constructed, 2. permission for completion of same and all associated site works
for proposed works which will include a solar farm on an area of approximately 27.0 hectares, comprising photovoltaic panels on ground mounted frames, 1 No., onsite 38kV substation, an energy storage system (4 No. units), 10 No. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 No. storage containers, CCTV, a temporary construction stage wheelwash system and all ancillary development works. Elgin Energy Services Ltd are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operational period of 35 years). The planning application incudes a Natura Impact Statement